I haven't done an update devoted to our house in a while...I also haven't posted any photographs. That's because I have misplaced the cable that connects the camera to the computer, but I hope to find it this weekend. The number of places I where need to look is slowly dwindling.
I took Wednesday off work to help with the house and we made great progress. We finished laying the subfloor and putting up all the beams for the upper floor of the house. Now that doesn't sound like much, but we worked from 9:30 am to 7:00 pm. Yesterday, Charles put up three exterior walls, leaving him only one to do today. He will also probably finish the joist hangers for the upstairs floor.
Next week, Charles will start building stairs. We need one set at the front door, one at the back door, and one to go upstairs! The subfloor upstairs will be far less involved than downstairs - downstairs has tongue and groove flooring sheets, both glued and nailed in place. Upstairs will have less traffic, so it's just plain old plywood sheets and only nailed in place. Plus with the hole in the middle of the upstairs, there's just plain less subflooring to put down.
Our aim is still to have first two layers of "skin" in place before the end of October. That's one layer of plywood all over the house, and a layer of house wrap. That way it will at least be weather-resistant as we go into winter. At the beginning of November, we will install temporary electricity on site, so we will have light through these early nights, and get going on windows, doors and metal siding and roofing. By the end of November we will be moved in, by hook or by crook. Maybe by flashlight!
The contractor also arrived Wednesday morning and started installing our septic tank. Before they leave they will also complete our driveway/parking area.